Structural Welding Quote

Structural Welding Quote Example — $6K Steel Staircase

A four-person structural shop in central Ohio needed a complete bid for an interior steel staircase in a two-story office renovation. The GC spec called for 14 treads, a mid-landing, pipe handrail with OSHA-compliant picket spacing, and diamond-plate treads on A36 steel. The shop estimated 16 hours of fabrication and 4 hours of field installation for roughly 1,200 lbs of steel. IronKit generated the full bid with itemized line items, scope notes, and exclusions in under 12 minutes. The GC signed off the same day — the shop owner said it would have taken him an entire evening to put together the same package by hand.
Document Preview
Welding Quote — Generated by IronKit

Project Details

ProjectInterior steel staircase — 2-story office renovation
LocationColumbus, OH (Midwest)
MaterialASTM A36 structural steel
Weight~1,200 lbs
CodeOSHA 1910.25 guardrail, IBC 2021 egress stair

Itemized Estimate

DescriptionQtyUnitRateAmount
C10×15.3 stringers, 14'-6" ea2ea$265.00$530.00
Diamond plate treads, 36"×11"14ea$62.00$868.00
Landing frame — W8×24 + plate1ls$480.00$480.00
1-1/2" Sch 40 pipe handrail42lf$18.00$756.00
3/4" sq bar pickets @ 4" o.c.68ea$6.50$442.00
Base plates w/ anchors4ea$45.00$180.00
Shop fabrication16hr$72.00$1,152.00
Field installation4hr$85.00$340.00
Primer coat (shop-applied)1ls$180.00$180.00
Subtotal$4,928.00
Overhead & Insurance (12%)$591.00
Profit (15%)$828.00
Total$6,347.00

Terms

  • Quote valid for 30 days from date of issue.
  • Payment: 50% upon acceptance, 50% upon completion.
  • Lead time: 3–4 weeks from signed PO.

Exclusions

  • Finish paint (by others)
  • Engineering and shop drawings
  • Concrete work and embed plates
  • Permits and inspections

Frequently Asked Questions

What does this $6K staircase quote include?
Materials (stringers, treads, handrail, pickets, base plates), shop fabrication labor, field installation, and shop-applied primer. Overhead and profit are broken out separately at 12% and 15%.
How long does it take IronKit to generate a structural quote?
Under 15 minutes. You enter the project basics — steel weight, member sizes, labor estimate — and IronKit builds the full bid document with line items, terms, and exclusions.
Can I edit the quote after IronKit generates it?
Yes. Every field is editable. Most shops adjust a line item or two, then export to PDF and send it to the GC within an hour of generating.