Schedule 40 Pipe Welding Quote — $18K Plant Expansion

A power plant contractor in the Southeast needed a fast turnaround quote for a mixed-diameter pipe run — 4" and 6" Schedule 40 A106 — as part of a cooling water expansion. The run included 260 linear feet of pipe total, with 18 butt welds on the 6" line and 14 on the 4" line. Shop spool fabrication was done off-site with field fit-up and final welds on location. IronKit separated the shop and field labor automatically when the user specified both locations. Total turn time from the quote request to the signed PO was 48 hours — the plant manager needed the work done during a scheduled outage window.
Document Preview
Welding Quote — Generated by IronKit

Project Details

ProjectCooling water pipe expansion — coal-fired power plant
LocationAlabama (Southeast)
MaterialASTM A106 Gr B, 4" and 6" Sch 40
Welds18 × 6" butt + 14 × 4" butt (32 total)
ScopeShop spool fabrication + field erection

Itemized Estimate

DescriptionQtyUnitRateAmount
6" Sch 40 A106 pipe160lf$14.50$2,320.00
4" Sch 40 A106 pipe100lf$8.75$875.00
6" weld fittings10ea$85.00$850.00
4" weld fittings8ea$48.00$384.00
Flanges (mixed sizes)8ea$95.00$760.00
Gasket and bolt kits8set$36.00$288.00
Pipe supports18ea$55.00$990.00
Shop spool fab (18 welds)32hr$95.00$3,040.00
Field weld labor (14 welds)28hr$105.00$2,940.00
Hydro test1ls$850.00$850.00
RT exam (32 welds)32ea$75.00$2,400.00
Subtotal$15,697.00
Overhead & Insurance (12%)$1,884.00
Profit (15%)$2,637.00
Total$20,218.00

Terms

  • Quote valid for 14 days (outage pricing).
  • Payment: Net 15 from completion.
  • Shop spool delivery: 2 weeks from PO.

Exclusions

  • Insulation and lagging
  • Scaffolding and crane (by plant)
  • Shutdown/lockout coordination
  • Valve supply (by owner)

Frequently Asked Questions

Why is field weld labor more expensive than shop?
Field welds require working in-position on installed pipe — harder access, more setup time, and typically slower travel speed. Shop welds can be rotated to optimal position, so the hourly rate is lower and the production rate is higher.
Does IronKit handle mixed-diameter pipe runs?
Yes. Enter each pipe size separately and IronKit prices them independently with the correct fittings, weld counts, and labor hours for each diameter.
What is the typical lead time for pipe spool fabrication?
Shop spool fabrication for this volume typically takes 2–3 weeks from signed PO, depending on material availability. IronKit notes the lead time in the terms section.