Pipe Welding Quote

Pipe Fabrication Takeoff — $31K Process Piping Package

A Houston process piping shop used IronKit to generate a bid for a water treatment facility expansion. The scope covered 3 t and 4 t Sch 40 carbon steel pipe spools — 38 butt weld joints, 8 socket weld connections, and miscellaneous flanged connections. IronKit counted the weld joints by size and process, generated the material take-off from nominal pipe sizes and flange weights, and produced a clean $31,200 bid.
Document Preview
Welding Quote — Generated by IronKit

Project Details

ProjectWater treatment facility expansion — process piping
LocationHouston, TX
Material3 t and 4 t A106 Gr B Sch 40 carbon steel pipe
Weld Joints38 butt welds + 8 socket welds + 4 flanged
CodeASME B31.3, AWS D1.1

Itemized Estimate

DescriptionQtyUnitRateAmount
4 t Sch 40 pipe — 240 t240lf$18.50$4,440.00
3 t Sch 40 pipe — 180 t180lf$14.80$2,664.00
4 t slip-on flanges 150# RF — 4 ea4ea$95.00$380.00
3 t slip-on flanges 150# RF — 4 ea4ea$75.00$300.00
4 t Sch 40 elbows — 16 ea16ea$48.00$768.00
3 t Sch 40 elbows — 12 ea12ea$32.00$384.00
4 t×3 t concentric reducers — 6 ea6ea$42.00$252.00
Misc fittings and adapters1ls$25.00$25.00
Weld neck flanges (field) 150# — 4 ea4ea$88.00$352.00
Bolts, gaskets, thread sealant1ls$380.00$380.00
Shop spool fabrication — 60 hrs @ $88/hr60hr$88.00$5,280.00
Butt weld 4 t — 24 joints @ ~1.5 hrs36hr$95.00$3,420.00
Butt weld 3 t — 14 joints @ ~1.2 hrs17hr$92.00$1,564.00
Socket weld assembly — 8 joints @ 0.5 hrs4hr$88.00$352.00
Field erection — 24 hrs @ $98/hr24hr$98.00$2,352.00
Hydro test (by others)0ls$0.00$0.00
Subtotal$22,913.00
Overhead & Insurance (15%)$3,437.00
Profit (18%)$4,743.00
Total$31,093.00

Terms

  • Quote valid for 30 days.
  • Payment: 40% upon material order, 40% upon spool delivery, 20% upon completion.
  • Lead time: 4 weeks from approved isometric drawings.

Exclusions

  • Weld neck flanges (4 t×4 t, field supply)
  • Welding inspector (provided by owner)
  • Hydro test water, equipment, and certification
  • Paint, wrap, or cathodic protection
  • Engineering and pipe stress analysis
  • Site field measuring (spool lengths by others)
  • Special flanges or class 300+ fittings

Frequently Asked Questions

How does IronKit count weld joints for process piping?
IronKit takes the pipe sizes and quantities you enter and calculates the number of butt weld joints by counting the number of spools and fittings. 3 t and 4 t spools typically have one joint per spool end, plus joint connections between spools. The calculator applies estimated weld time per joint size and process (SMAW, GTAW, GMAW) to build the labor estimate.
Why separate shop spool fabrication from field erection?
Process piping shops often do their fabrication in the shop (controlled environment, better quality) and then send field welders to the site for erection. Shop rates and field rates are different, and shop fabrication hours are more predictable. Separating them lets the customer see exactly where the cost is — and lets the shop owner track shop vs. field margin.
What is the difference between Sch 40 and Sch 80 for material takeoff?
Wall thickness. Sch 40 has thinner walls than Sch 80 at the same diameter, so it ts lighter and cheaper per foot. Sch 80 is used for higher pressure service. IronKit calculates pipe weight per foot using ASME B36.10M dimensions — automatically adjusts the material cost based on the schedule you specify.
Can IronKit handle stainless and chrome-moly pipe too?
Yes — specify the material (304/316 stainless, P91 chrome-moly) and IronKit adjusts the material cost, weld process, and labor rate. Chrome-moly requires GTAW root + SMAW fill (no GMAW or FCAW), and the weld time is significantly higher due to the preheat and post-weld requirements.

Generate Your Own — In 3 Minutes

Generate your own welding quote in 3 minutes — free for 14 days.

Start Free Trial $29/mo after trial. Cancel anytime.
Start Free Trial — 14 Days Free