Structural Welding Quote

Steel Warehouse Quote Example — $62K Structural Package

A South Carolina structural steel fabricator quoted a 6,400 sqft pre-engineered warehouse shell for a logistics company. The package included main rigid frames, endwall frames, purlins, girts, and all connections — approximately 60 tons of steel. The GC wanted a single line-item breakdown that separated primary framing from secondary members and erection. IronKit generated the complete bid in 15 minutes with clear categories. The fabricator said the biggest time-saver was the automatic connection hardware calculation — counting clips and bolts for 60 tons of steel usually takes half a day.
Document Preview
Welding Quote — Generated by IronKit

Project Details

ProjectPre-engineered warehouse shell — 6,400 sqft
LocationGreenville, SC (South)
MaterialASTM A992 / A36 mixed
Tonnage~60 tons
Bay80'×80', 24' eave height, 6 bays @ 25' spacing

Itemized Estimate

DescriptionQtyUnitRateAmount
Rigid frame columns W12×5812ea$890.00$10,680.00
Rigid frame rafters W16×4012ea$720.00$8,640.00
Endwall columns W8×248ea$385.00$3,080.00
Roof purlins C8×11.548ea$165.00$7,920.00
Wall girts C6×8.236ea$95.00$3,420.00
Base plates and anchor bolts20ea$165.00$3,300.00
Connection hardware1ls$2,880.00$2,880.00
Shop fabrication120hr$72.00$8,640.00
Field erection (4-man crew)56hr$145.00$8,120.00
Shop primer1ls$2,450.00$2,450.00
Subtotal$59,130.00
Overhead & Insurance (12%)$7,096.00
Profit (15%)$9,934.00
Total$76,160.00

Terms

  • Quote valid for 30 days.
  • Payment: 25% deposit, progress billing, 10% retainage released at substantial completion.
  • Lead time: 10–12 weeks from approved drawings.

Exclusions

  • Metal roof and wall panels
  • Engineered sealed drawings
  • Concrete foundations
  • Overhead doors and framing
  • Crane rental (by GC)

Frequently Asked Questions

What is included in a $62K warehouse steel quote?
Primary rigid frames, endwall framing, purlins, girts, all base plates and connections, shop fabrication, field erection, primer, and hardware. Panels, foundations, and engineering are excluded.
How does IronKit price 60 tons of steel?
IronKit uses per-member pricing based on weight, section size, and length — then adds shop labor, field erection, and primer as separate line items. The subtotal is marked up for overhead (12%) and profit (15%).
Can IronKit handle pre-engineered metal building quotes?
Yes. You can enter rigid frame specs, bay spacing, and eave height. IronKit generates the full member schedule and cost estimate. It does not produce engineering calculations — those require a PE.

Generate Your Own — In 3 Minutes

Generate your own welding quote in 3 minutes — free for 14 days.

Start Free Trial $29/mo after trial. Cancel anytime.
Start Free Trial — 14 Days Free